Thursday 9 May 2019

Balcony Project Week 2

Whilst it may have been more than 7 days since the last weekly update, there has been a bank holiday in the way. However progress has been made. After a visit of the local council building control inspector the holes are now about a foot deeper down to below the level of the drains.

Forward progress this week has been filling the holes with concrete and measuring/marking the back wall ready for the steel support pads to be inserted. Today Max from local firm WM Ironwork visited to do the measurements for the structural steels.

Next






The colour decisions have been made “dark grey pearl” for the support leg collars and front edge facing covers. This will blend with the “stone” decking, white under roof and RSJ pillars.

Things may go quiet for a while whilst the steels are cut and shaped to plan. The tricky bit of the steels is the staircase that has to be specificity customised for the hight/travel.

Design conundrum

What we have seen since the dig has progressed is the level of rot in the support pillars. Two out of the five front pillars at the front two show significant rot at ground level that goes some what to explain the sagging of the existing structure.

The existing 2008 built structure is wood and showing the impact of age, water and poor designs.  The original support should have been built on top of a water proof support similar to this diagram....



Also the joists are showing the start of rain exposure damage caused by external exposure and run through.


The new structure is to have a waterproof under decking laid on top of the joists preventing such damage in the futures. However the conundrum is do we use joists made of recycled plastic or traditional wood. Liking the idea of supporting the alternative wood materials industry but they do cost three times as much per metre.

After some thought we are likely to go for the composite decking with plastic lumber under support as this will be the rain impacted area.