Big progress this "week". The steels arrived and were put up in a day. Next day wooden joists went in and electrician started running the wires for the illuminations. Boarding and deck fibre glassing also done.
Next week the Stairs structure is due and the decking gets a gel coat followed by decking boards. The under balcony space will be having paving laid.
Going to rearrange the down pipes from the roof & gutters above the balcony so that we don't need a down pipe in the middle of the decking. The decking will drain down pipes attached to each of the pillars at the front and will be enclosed by a collar.